What is the going rate per foot for sheetrock in northern states to hang and finish?
Question:
Answers:
Try to google it, they have alot of info.
k
Tapered edge. Cut ends. Labor includes cutting board around electrical boxes and obstacles, installing on wall studs or ceiling joists 8' to 12' above floor level, joint tape, three coats of joint compound and finish sanding. Material includes 1/2 gallon of premixed joint compound per 100 square feet, 38 linear feet of 2" perforated joint tape per 100 square feet, 1/2 pound of drywall screws per 100 square feet and 10% waste.
3/8" x 4'x8', ceilings 1.63 SF
3/8" x 4'x8', walls 1.33 SF
1/2" x 4'x8', ceilings 1.68 SF
1/2" x 4'x8', walls 1.38 SF
1/2" x 4'x9', ceilings 1.68 SF
1/2" x 4'x9', walls 1.38 SF
1/2" x 4'x10', ceilings1.68 SF
1/2" x 4'x10' walls, 1.38 SF
1/2" x 4'x12', ceilings 1.68 SF
1/2" x 4'x12', walls 1.38 SF
1/2" x 54" x 12', ceilings 1.73 SF
1/2" x 54" x 12' walls, 1.43 SF
1/2" x 4' x12' ceilings, sag resistant 1.68 SF
1/2" x 4' x 12' soffit board, 2.36 SF
1/2" panels on ceilings, no tape or finish 1.00 SF
1/2" panels on walls, no tape or finish .80 SF
Arches, soffits, recesses, columns, angles 1.79 SF